The Part Submission Warrant (PSW) summarizes the entire PPAP package. Governed by the AIAG PPAP standard, a PSW is required for each part number unless otherwise stated by the customer.
A full PPAP submission can include up to 18 elements, dimensional results, material certifications, process capability studies and more, and the PSW is the cover document that ties them together, declaring that every required element has been completed and that the part conforms to the customer's requirements. Get our free Part Submission Warrant template for Excel or as a fillable PDF.
Part Information
Organization Manufacturing Information
Submission Information
Reason for Submission
Check the appropriate box:Requested Submission Level
Identify the submission level requested by your customer.
| Level | What's included |
| Level 1 |
Part Submission Warrant (PSW) only |
| Level 2 |
PSW with product samples and limited supporting data |
| Level 3 |
PSW with product samples and complete supporting data |
| Level 4 |
PSW and other requirements as defined by the customer |
| Level 5 |
PSW with product samples and complete supporting data available for review at the supplier's manufacturing location |
Learn more about PPAP submission levels.
Declaration
Download our free PPAP template, or get just the part submission warrant below.
Organizing the dimensional data behind your PSW
The PSW declares that a part conforms, but that declaration rests on the dimensional results collected during inspection, each characteristic on the drawing measured, checked against tolerance, and traceable back to a specific requirement. Ideagen Quality Control (formerly InspectionXpert) balloons your part drawing, imports measurement results from a CMM or hand tools, and organizes that dimensional data so it's ready to support your PSW and the rest of your PPAP package, instead of being assembled by hand from a spreadsheet for every submission.
Get free access for 14 days, or download our free PPAP template, or get just the part submission warrant below.
Frequently asked questions
The Part Submission Warrant (PSW) is the summary document for a PPAP package, governed by the AIAG PPAP standard. It declares that a part conforms to the customer's requirements and that all required PPAP elements have been completed, and is required for each part number unless otherwise stated by the customer.
A PSW is required for each part number submitted for PPAP approval, unless the customer states otherwise. The specific reason for submission, such as an initial submission, an engineering change, or a tooling transfer, is documented directly on the PSW.
Submission levels range from Level 1 (PSW only) to Level 5 (PSW with product samples and complete supporting data available for review at the supplier's manufacturing location), with Levels 2 through 4 covering varying degrees of supporting data and customer-defined requirements in between.